top of page
Click the buttons below for more detail

RODNEY PARHAM UPDATE 10/11/23

​

The city is still planning to finish the entire project in the summer of 2024.

 

Redstone is finishing some last items in Phase 1 on Rodney Parham south of Pleasant Valley Dr.

When those small items are finished the final surface pavement and striping will be installed and Phase 1 will be substantially complete.

​

Redstone is currently gearing up to begin construction on Phase 2 which is north of Pleasant Valley Drive.  

 

Phase 3 will begin following the conclusion of Phase 2.  Phase 3 consists of the reconstruction of Rodney Parham Rd/Pleasant Valley Dr intersection.

​

Signs indicate the Cantrell phase 1 construction should be complete in 2023.  

bottom of page